Activities

Activities 2020-03-20T14:43:43+00:00
2406, 2020

June/July Activity Update

Preparation activities for remediation work continued in June. Activities included set up and activation of air monitoring stations, a meteorological station, and installation of equipment decontamination pad and truck wash [...]

2005, 2020

April/May Activity Update

Preparation for remediation activities continued at the site throughout April and into May. Activities included adding additional safety markers, preparing backfill materials, setting up traffic control, and safely removing debris [...]

304, 2020

March Activity Update

ComEd is preparing to start remediating the 215 N Wyman Street site. Activities in March included: Finalization of Project Plans Continued work on utility relocation Site preparation

1702, 2020

February Activity Update

Utility relocation is planned to continue through March 2020 Remediation work is scheduled to start in February 2020, pending design and permit approval

1211, 2019

November Activity Update

Utility relocation work will start this month. Remediation work is planned to start in January 2020. In addition to north side sidewalk on Mulberry Street being closed for duration of [...]

310, 2019

Fall 2019 Update

Utility Relocation will begin mid-October 2019. Remediation bids have been submitted and are currently being evaluated. Remediation work is scheduled to begin in November/December 2019.

Load More Posts